Abstract
As part of the study, the basic variants of the introduction of DV 2x110 kV Trogir - Podi into TS Trogir were processed, for the foreseeable year of entry into operation of the DV 2x110 kV in question (2013) and the nominal year 2020. In doing so, the existing plans for the development of the surrounding influential transmission network and the currently foreseeable scope of construction of potential new facilities were taken into account. Also, an analysis was performed and a proposal was made for a possible option for the reconstruction of the 110 kV network from TS Podi to TS Bilica, and the fitting of a new DV 110 kV (south route) Trogir-Marina-Rogoznica-Podi/Ražine/Bilice.

Full Professor | Department of Power Grids and Substations
Full professor at the Faculty of Electrical Engineering, Mechanical Engineering, and Naval Architecture in Split exeperienced in transmission and distribution networks, renewable energy sources (RES), power system planing and economics

Full Professor | Department of Power Grids and Substations
Researcher and a full professor at the Faculty of Electrical Engineering, Mechanical Engineering and Naval Architecture in Split. His research interests include power system optimization and planning, RES integration, electricity market modeling.

Junior Researcher
My research interests optimal RES connection, grid-compliance testing.